To: Cochise County Planning and Zoning Commission and Cochise County Board of Supervisors We, the undersigned residents and property owners of Cochise County, oppose the Special Use Authorization sought by Tombstone Resources L.L.C. for a nine-building data center on 57 parcels along U.S. Highway 191 near Apache Station. Our families depend entirely on groundwater from an aquifer the State of Arizona has already declared over-drafted. Wells in the Sulphur Springs Valley are going dry, and residents are re-drilling and hauling water today. The developer has not disclosed how much water or power this project will use. It would place industrial buildings up to 40 feet tall, battery storage yards, and gas generators within 150 to 300 feet of homes, on a site outside any fire district.
We ask the County to: (1) deny the Special Use Authorization for this project; (2) require full public disclosure of water and power demand before any hearing; (3) protect rural groundwater by adopting a net-zero water rule or a moratorium on data centers in our basins.
Updates
Over 7000 strong: now one more step before Friday
November 19, 2026
Friends of our communities in the Sulphur Springs Valley, Cochise Stronghold, Chiricahua National Park, and the Sandhill Cranes. We did it together: 7,018 signatures against SU26-22, the 6-gigawatt SpaceX data center and the "largest single-site" battery plant proposed on 747 acres beside the Willcox Playa. That is no small thing. In just over three weeks, neighbors from Pearce, Sunsites, Cochise, Willcox, Benson, Sierra Vista, Bisbee and Douglas and all over Arizona and the country have stood up together. Families who grew up here, crane watchers, ranchers, retirees and visitors who love this valley have all said the same thing: not here. Now we need your voice in the County's own record. The Planning and Zoning Commission votes on December 9. Its decision is final unless appealed, and an approval runs with the land, forever. The petition shows our numbers. A comment in the County's record shows the Commission exactly why. GET YOUR COMMENT IN BY TOMORROW, NOV. 20, TO BEAT THE HOLIDAY DEADLINE. It takes about three minutes. Our comment builder writes it with you, then takes you straight to the County's form: stopcochisedatacenter.com If you need a reason, the application gives you plenty: • No traffic study, for 5,500 workers on two-lane Highway 191 • No noise study, put off until "building permit" • No geology study, though the site sits in a State-mapped earth fissure area • No emergency plan, on a site "outside any fire district" • About 90 megawatts of gas generators, with no emission limits • It says "no production well." The State lists 28 registered wells on the site • The promises of lower bills and big payments are not in the application at all We are told the details will "come later." But later is too late. The vote on December 9 decides whether this land is suitable. Once it is approved, it cannot be taken back. THREE THINGS YOU CAN DO TODAY 1. Write your comment at stopcochisedatacenter.com (by Nov. 20). 2. Forward this email to five people who love this valley. Ask them to sign: go.ipetitions.com/ahs5Eq 3. Save the date: Wednesday, December 9, 2 p.m., Board of Supervisors Meeting Room, 1415 W. Melody Lane, Building G, Bisbee. You can also speak online. Every seat filled tells the Commission who this valley belongs to. This valley, our wells, our dark skies, our air and our health are worth protecting. 7,018 of us agree. Let's make sure the Commission hears every one of us. Ask the Commission to deny SU26-22. With gratitude and determination, Stop Cochise Data Center stopcochisedatacenter.com [email protected]
Reached 5,000 supporters
November 17, 2026
4000 Strong: what's changed, and what to do before Nov 20
November 14, 2026
Title: 4,000 strong: what’s changed, and what to do before Nov. 20 Thank you! More than 4,000 of you have signed in under three weeks. The application has changed three times since this petition started, so here are the current facts: The current application covers 31 parcels on about 747 acres beside the Willcox Playa and Apache Station. It’s a 6-gigawatt AI data center plus a 24 gigawatt-hour battery plant, which the applicant calls “the largest single-site BESS system in the world.” SpaceX has confirmed it’s behind the project. The site is in the Willcox Active Management Area. The application says “No production well,” but the State’s Well Registry lists 28 registered wells on those parcels. No legal water right is identified for construction water or the “trucked water” it plans to use. The County’s emergency planners recommended six conditions on Nov. 12, including a study of whether local responders can handle a battery fire. They estimated the site’s emergency plan could take 6 to 12 months. The vote is Dec. 9. What you can do now: Send a comment by Fri., Nov. 20 to beat the holiday deadline. The official deadline is Fri., Nov. 27 at noon. Send our ready-made letter to the Governor, the Attorney General and our members of Congress. It takes five minutes and has a fillable version at stopcochisedatacenter.com. Come to the hearing: Wed., Dec. 9, 2 p.m., 1415 W. Melody Lane, Bisbee, or on Microsoft Teams. All three application packages, our comparisons and the emergency planners’ findings are at stopcochisedatacenter.com. Stop Cochise Data Center
Reached 2,500 supporters
November 6, 2026
Reached 1,000 supporters
November 1, 2026
Reached 500 supporters
October 28, 2026
Reached 250 supporters
October 27, 2026
Reached 100 supporters
October 25, 2026
2,512 Comments
Our groundwater is not renewable. Our wells are getting drier and deeper. Our water and electrical bills are getting higher almost every year.
This is about money and investor interests, not what serves we the people. Hyperscale data centers use water and power. The huge resources an industrial project brings to bear to make it seem like this isn't the case aren't something our small rural county can easily counter. This project is on a fast track with huge funding. If you oppose it, now is the time to act.
This area is my home. This AI Center does NOT belong in our desert all ready short on water and resources. Human beings, pets, herd animals and wildlife LIVE HERE.
Not a good fit for an area that already has extreme water shortages. This area will be a ghost town if these facilities are allowed
Protect our vital ecosystems
We must save our water and environment for the next generation and the animals.
I don't know why anyone would want this here. Not good for nature an our treasured small town peaceful area.
Sign Petition
We never post to your account. Social sign-in is used only to verify your signature.
Add a comment?
Your signature will be added via . Tell others why you're signing — it's optional.
By signing, you accept our Terms and Privacy Policy and agree to occasional emails about petitions. Unsubscribe anytime.
Share this petition
Share this petition to help it reach more people.
Your share link
Couldn't copy automatically. Long-press to copy:
To: Cochise County Planning and Zoning Commission and Cochise County Board of Supervisors We, the undersigned residents and property owners of Cochise County, oppose the Special Use Authorization sought by Tombstone Resources L.L.C. for a nine-building data center on 57 parcels along U.S. Highway 191 near Apache Station. Our families depend entirely on groundwater from an aquifer the State of Arizona has already declared over-drafted. Wells in the Sulphur Springs Valley are going dry, and residents are re-drilling and hauling water today. The developer has not disclosed how much water or power this project will use. It would place industrial buildings up to 40 feet tall, battery storage yards, and gas generators within 150 to 300 feet of homes, on a site outside any fire district.
We ask the County to: (1) deny the Special Use Authorization for this project; (2) require full public disclosure of water and power demand before any hearing; (3) protect rural groundwater by adopting a net-zero water rule or a moratorium on data centers in our basins.
Updates
Over 7000 strong: now one more step before Friday
November 19, 2026
Friends of our communities in the Sulphur Springs Valley, Cochise Stronghold, Chiricahua National Park, and the Sandhill Cranes. We did it together: 7,018 signatures against SU26-22, the 6-gigawatt SpaceX data center and the "largest single-site" battery plant proposed on 747 acres beside the Willcox Playa. That is no small thing. In just over three weeks, neighbors from Pearce, Sunsites, Cochise, Willcox, Benson, Sierra Vista, Bisbee and Douglas and all over Arizona and the country have stood up together. Families who grew up here, crane watchers, ranchers, retirees and visitors who love this valley have all said the same thing: not here. Now we need your voice in the County's own record. The Planning and Zoning Commission votes on December 9. Its decision is final unless appealed, and an approval runs with the land, forever. The petition shows our numbers. A comment in the County's record shows the Commission exactly why. GET YOUR COMMENT IN BY TOMORROW, NOV. 20, TO BEAT THE HOLIDAY DEADLINE. It takes about three minutes. Our comment builder writes it with you, then takes you straight to the County's form: stopcochisedatacenter.com If you need a reason, the application gives you plenty: • No traffic study, for 5,500 workers on two-lane Highway 191 • No noise study, put off until "building permit" • No geology study, though the site sits in a State-mapped earth fissure area • No emergency plan, on a site "outside any fire district" • About 90 megawatts of gas generators, with no emission limits • It says "no production well." The State lists 28 registered wells on the site • The promises of lower bills and big payments are not in the application at all We are told the details will "come later." But later is too late. The vote on December 9 decides whether this land is suitable. Once it is approved, it cannot be taken back. THREE THINGS YOU CAN DO TODAY 1. Write your comment at stopcochisedatacenter.com (by Nov. 20). 2. Forward this email to five people who love this valley. Ask them to sign: go.ipetitions.com/ahs5Eq 3. Save the date: Wednesday, December 9, 2 p.m., Board of Supervisors Meeting Room, 1415 W. Melody Lane, Building G, Bisbee. You can also speak online. Every seat filled tells the Commission who this valley belongs to. This valley, our wells, our dark skies, our air and our health are worth protecting. 7,018 of us agree. Let's make sure the Commission hears every one of us. Ask the Commission to deny SU26-22. With gratitude and determination, Stop Cochise Data Center stopcochisedatacenter.com [email protected]
Reached 5,000 supporters
November 17, 2026
4000 Strong: what's changed, and what to do before Nov 20
November 14, 2026
Title: 4,000 strong: what’s changed, and what to do before Nov. 20 Thank you! More than 4,000 of you have signed in under three weeks. The application has changed three times since this petition started, so here are the current facts: The current application covers 31 parcels on about 747 acres beside the Willcox Playa and Apache Station. It’s a 6-gigawatt AI data center plus a 24 gigawatt-hour battery plant, which the applicant calls “the largest single-site BESS system in the world.” SpaceX has confirmed it’s behind the project. The site is in the Willcox Active Management Area. The application says “No production well,” but the State’s Well Registry lists 28 registered wells on those parcels. No legal water right is identified for construction water or the “trucked water” it plans to use. The County’s emergency planners recommended six conditions on Nov. 12, including a study of whether local responders can handle a battery fire. They estimated the site’s emergency plan could take 6 to 12 months. The vote is Dec. 9. What you can do now: Send a comment by Fri., Nov. 20 to beat the holiday deadline. The official deadline is Fri., Nov. 27 at noon. Send our ready-made letter to the Governor, the Attorney General and our members of Congress. It takes five minutes and has a fillable version at stopcochisedatacenter.com. Come to the hearing: Wed., Dec. 9, 2 p.m., 1415 W. Melody Lane, Bisbee, or on Microsoft Teams. All three application packages, our comparisons and the emergency planners’ findings are at stopcochisedatacenter.com. Stop Cochise Data Center
Reached 2,500 supporters
November 6, 2026
Reached 1,000 supporters
November 1, 2026
Reached 500 supporters
October 28, 2026
Reached 250 supporters
October 27, 2026
Reached 100 supporters
October 25, 2026
2,512 Comments
We've already seen the negative impacts on ground water and electric bills in areas where data centers are going in. Bad enough for county leadership to consider a facility that will so dramatically affect the utility bills of local residents, but worse is the impact this would have on ground water. Leadership at all levels in Arizona have long encouraged conservation and careful water usage, and then they go and consider an application like this? Please don't do it!
Our groundwater is not renewable. Our wells are getting drier and deeper. Our water and electrical bills are getting higher almost every year.
This is about money and investor interests, not what serves we the people. Hyperscale data centers use water and power. The huge resources an industrial project brings to bear to make it seem like this isn't the case aren't something our small rural county can easily counter. This project is on a fast track with huge funding. If you oppose it, now is the time to act.
This area is my home. This AI Center does NOT belong in our desert all ready short on water and resources. Human beings, pets, herd animals and wildlife LIVE HERE.
Not a good fit for an area that already has extreme water shortages. This area will be a ghost town if these facilities are allowed
Protect our vital ecosystems
We must save our water and environment for the next generation and the animals.
I don't know why anyone would want this here. Not good for nature an our treasured small town peaceful area.
Help this petition grow
Share it with friends to help reach 10,000 signatures.
Sign Petition
We never post to your account. Social sign-in is used only to verify your signature.
Add a comment?
Your signature will be added via .
Tell others why you're signing — it's optional.
Signing with Google or Facebook verifies your signature instantly — no email needed.
By signing, you accept our Terms and Privacy Policy and agree to occasional emails about petitions. Unsubscribe anytime.
Share this petition
Share this petition to help it reach more people.
Your share link
Couldn't copy automatically. Long-press to copy:
Petitions like this
Other petitions you might want to support
Make your voice count today!
Scan to share
Anyone who scans this can sign the petition.
We've already seen the negative impacts on ground water and electric bills in areas where data centers are going in. Bad enough for county leadership to consider a facility that will so dramatically affect the utility bills of local residents, but worse is the impact this would have on ground water. Leadership at all levels in Arizona have long encouraged conservation and careful water usage, and then they go and consider an application like this? Please don't do it!