Plea from Amrapali Zodiac members for completion and handover of long delayed appartment
We had purchased a flat in a project of Amrapali builders known as "Amrapali Zodiac Phase 1" in Mid of 2010 with a promise to possession by 2012 March. But till date we have not got the possession after 5 years of purchase inspite of paying near about 80% of amount on time as asked by builder.
Please find the attached snaps which shows current state. Practically there has been no work done in past one year. What is this? Is it some kind of joke with us? We have purchased this flat with my hard earned money.
We all residents have met personally in so many meeting with Amrapali and received false promises. After meeting personally both times in April 2014 and April 2015 and at both occasion i was committed handover of my flat in the month of July/Aug of the respective year of meeting but it foresee that Amrapali is not serious about handing over our flat. Also, about the penalty, i was told in our personnel meeting that Amrapali is not liable to pay penalty amount after Sept 13 since it was delayed due to Govt. order, where as you can see in the attached snap that there has been considerable delay on Amrapali. It was not our fault that Amrapali did not have necessary clearance at the time of sales. Also, Amrapali is citing NGT order as reason of stopped construction whereas NGT order says that current construction should not be stopped and only new construction should be stopped.
We booked our flat long back in 2009-2011 with promise to deliver it by 2012 and its been near about 5 years since then. We have already paid majority amount and cannot sustain like this as we all are paying rent/EMI. Also, all delays should be accompanied by appropriate penalty amount as mentioned in contract and delay should not cross this September 2015.
So, request all to join the petition to ask Amrapali builders not to take advantage of poor consumers and handover our apartment in complete finished state with appropriate penalty amount.
Updates
June 16, 2015
I have compiled the documentation regarding the construction delays and forwarded it to the legal team for review. We are currently finalizing a formal letter to submit to the authorities to address the inaccurate claims about the NGT order. Future efforts will focus on securing a direct meeting with the developers to demand a revised handover schedule.
June 16, 2015
The volume of support has now reached a level that allows me to formally request a meeting with the legal team overseeing the Amrapali insolvency process. I am finalizing the summary of our grievances to present alongside the petition during these upcoming discussions. Expect further details on the official response once we confirm the appointment.
38 Comments
I booked my flat in Jan 2013 with a promise that I will get possession in July 2013. However even after 2.5 years I have not got the possession and still I see no chance of getting possession in next one year after seeing the pace with which the Amrapali is doing the construction. Its becoming very hard to pay EMI as well as Rent at the same time. Also Amrapali is denying any penalty amount.
We booked our flat in Q tower in June 2009, we were promised that we will get the possession by June 2012. 3 year passed and we are still waiting to get one. We are really fed up now, after waiting for 3 additional years, the condition remain same. Can we put forward our voice to the court. Tried reaching out to the amrapalli guys we get an answer that just wait for 4-5 months and it will be done. Lets work together and get out of the problem.
I am ready to sign in for the petition
I also willing to sign and protest against the high headedness of Amrapali in handing over my booked flat no : A-1001
I am signing this petition because Builder is not ready my flat.
I am also signing for my flat N-706. I had booked my flat in Dec 2009 and the possession date was March 2012; final demand all inclusive was paid in Dec. 2014 and still no sign of getting my flat. Till 21.06.2015, Till date only wiring work and civil repair has been done. Every week I am personally going to site and meeting site incharge etc. and I have been told that they do not have tiles, slab for kitchen counter, UPVC material, material for modular kitchen etc. and god knows when they will get the material and finishing work will be completed. Despite making more than 100% payment, there is no sign of early possession. Even these people are not making payment of penalty amount, as agreed upon in BBA. No reason is given for non payment of penalty amount. I have dropped emails to Amrapali Management but there is no response.
This is really frustrating that the possession which was to be handed over in 24 months, is nowhere even after 48 months. We demand immediate possession and appropriate penalty for delay
Sign Petition
We never post to your account. Social sign-in is used only to verify your signature.
Add a comment?
Your signature will be added via . Tell others why you're signing — it's optional.
By signing, you accept iPetitions Terms of Service and Privacy Policy.
Share Petition
Don't stop at signing, share the petition link with friends to multiply our impact
Copy link or share directly
Plea from Amrapali Zodiac members for completion and handover of long delayed appartment
We had purchased a flat in a project of Amrapali builders known as "Amrapali Zodiac Phase 1" in Mid of 2010 with a promise to possession by 2012 March. But till date we have not got the possession after 5 years of purchase inspite of paying near about 80% of amount on time as asked by builder.
Please find the attached snaps which shows current state. Practically there has been no work done in past one year. What is this? Is it some kind of joke with us? We have purchased this flat with my hard earned money.
We all residents have met personally in so many meeting with Amrapali and received false promises. After meeting personally both times in April 2014 and April 2015 and at both occasion i was committed handover of my flat in the month of July/Aug of the respective year of meeting but it foresee that Amrapali is not serious about handing over our flat. Also, about the penalty, i was told in our personnel meeting that Amrapali is not liable to pay penalty amount after Sept 13 since it was delayed due to Govt. order, where as you can see in the attached snap that there has been considerable delay on Amrapali. It was not our fault that Amrapali did not have necessary clearance at the time of sales. Also, Amrapali is citing NGT order as reason of stopped construction whereas NGT order says that current construction should not be stopped and only new construction should be stopped.
We booked our flat long back in 2009-2011 with promise to deliver it by 2012 and its been near about 5 years since then. We have already paid majority amount and cannot sustain like this as we all are paying rent/EMI. Also, all delays should be accompanied by appropriate penalty amount as mentioned in contract and delay should not cross this September 2015.
So, request all to join the petition to ask Amrapali builders not to take advantage of poor consumers and handover our apartment in complete finished state with appropriate penalty amount.
Updates
June 16, 2015
I have compiled the documentation regarding the construction delays and forwarded it to the legal team for review. We are currently finalizing a formal letter to submit to the authorities to address the inaccurate claims about the NGT order. Future efforts will focus on securing a direct meeting with the developers to demand a revised handover schedule.
June 16, 2015
The volume of support has now reached a level that allows me to formally request a meeting with the legal team overseeing the Amrapali insolvency process. I am finalizing the summary of our grievances to present alongside the petition during these upcoming discussions. Expect further details on the official response once we confirm the appointment.
38 Comments
Kindly expedite delivery of R Tower. We can not afford paying rent as well as EMI for long time. As a well reputed builder, kindly honor your commitment and endure high quality delivery on time. I was assured delivery by October this year (R-1403). This is humble request to act fast and deliver as promised.
I booked my flat in Jan 2013 with a promise that I will get possession in July 2013. However even after 2.5 years I have not got the possession and still I see no chance of getting possession in next one year after seeing the pace with which the Amrapali is doing the construction. Its becoming very hard to pay EMI as well as Rent at the same time. Also Amrapali is denying any penalty amount.
We booked our flat in Q tower in June 2009, we were promised that we will get the possession by June 2012. 3 year passed and we are still waiting to get one. We are really fed up now, after waiting for 3 additional years, the condition remain same. Can we put forward our voice to the court. Tried reaching out to the amrapalli guys we get an answer that just wait for 4-5 months and it will be done. Lets work together and get out of the problem.
I am ready to sign in for the petition
I also willing to sign and protest against the high headedness of Amrapali in handing over my booked flat no : A-1001
I am signing this petition because Builder is not ready my flat.
I am also signing for my flat N-706. I had booked my flat in Dec 2009 and the possession date was March 2012; final demand all inclusive was paid in Dec. 2014 and still no sign of getting my flat. Till 21.06.2015, Till date only wiring work and civil repair has been done. Every week I am personally going to site and meeting site incharge etc. and I have been told that they do not have tiles, slab for kitchen counter, UPVC material, material for modular kitchen etc. and god knows when they will get the material and finishing work will be completed. Despite making more than 100% payment, there is no sign of early possession. Even these people are not making payment of penalty amount, as agreed upon in BBA. No reason is given for non payment of penalty amount. I have dropped emails to Amrapali Management but there is no response.
This is really frustrating that the possession which was to be handed over in 24 months, is nowhere even after 48 months. We demand immediate possession and appropriate penalty for delay
Help this petition grow
Share it with friends to help reach 50 signatures.
Sign Petition
We never post to your account. Social sign-in is used only to verify your signature.
Add a comment?
Your signature will be added via .
Tell others why you're signing — it's optional.
Signing with Google or Facebook verifies your signature instantly — no email needed.
By signing, you accept iPetitions Terms of Service and Privacy Policy.
Share Petition
Don't stop at signing, share the petition link with friends to multiply our impact
Petitions like this
Other petitions you might want to support
Make your voice count today!
Scan to share
Anyone who scans this can sign the petition.
Kindly expedite delivery of R Tower. We can not afford paying rent as well as EMI for long time. As a well reputed builder, kindly honor your commitment and endure high quality delivery on time. I was assured delivery by October this year (R-1403). This is humble request to act fast and deliver as promised.