Request to delay 4% registration fee until project's completion
48 Comments
A
Anonymous
11 years ago
I bought studio in 2014 & paid the 4% but nothing happened yet & they said I can't get my apartment in 2016 as agreement! :(
From Kuwait
A
Anonymous
11 years ago
I bought studio in 2014 & paid the 4% but nothing happened yet & they said I can't get my apartment in 2016 as agreement! :(
From Kuwait
S
Sikkander Amin
11 years ago
Featured
I booked the apartment in 2008 and am still waiting for delivery. I am not sure if the project will ever be completed. The registration fee should be taken only on handover after completion.
K
KRISHAN KANT AGARVAL
11 years ago
I've also invested in this project. And totally agree that the registration fee should be delayed till completion of full project as already too delayed for this project
J
Jean shenava
11 years ago
Worst decision I made in my life was to invest in Dubai Lagoon !
A
Anonymous
11 years ago
Why have RERA, DLD, Dubai Municipality, Dubai Government allowed Schon/TCM to continually mislead investors for 10 years? This is a partnership of companies that hasn't finished a single project in 10 years! How is it possible that they haven't been held accountable for holding investors money for 10 years with no sign of completion? Dubai needs to think about the damage this kind of "businessmen" do to its reputation. Expo 2020 is 5 years away and Dubai Lagoon is sending the wrong message about the safety of investments here.
A
Anonymous
11 years ago
I will gladly pay but I don't believe my developer intends to complete the project. It is already 8 years late.
I
Irma Bugarin
11 years ago
I support this petition. I am a buyer in zone 1.
G
Gerard Byrne
11 years ago
10 Years I have been waiting.
10 Years ago Pope John Paul 11 died, Angela Merkel became Germanys first Female Chancellor and the Burj Khalifa was just being started. No amount of compensation is going to be enough. Get on with it!!!
A
Anand Mohan
11 years ago
Really pathetic Situation. This developer keeps on dragging the dates of Project completion. Please do something Dubai Land Department for the DL Investors!
A
Anand Mohan
11 years ago
High time to intervene by Dubai
Land Department as many years passed by. So far very pathetic result from the Developer. Please do something for and on behalf of DL Investors!
I
Isobel Wales
11 years ago
I have been waiting for my apartment for over 5 years
B
Bob Brown
11 years ago
I would request the authorities not just to keep the registration fee payable at handover but also to refrain from capriciously changing the rules from day to day in all cases. Such actions don't help the real estate sector but greatly undermine people's trust and confidence in the sector when rules are whimsically changed and even applied retrospectively whenever it strikes the fancy of some authority.
This particular change has significant implications not just for end users and investors alike who have lost huge sums on projects that never materialized but also for those who have budgeted as per the previous practice (registration payment at handover) and now face a shortfall.
I would urge the authorities not to underestimate the importance of stability and clarity in the market and to try to work with people rather than against them through constructive regulations that are well thought out before implementation. Therefore, kindly reconsider this new demand at the earliest as it is very shortsighted and disappointing, and only harms the market.
D
David Carr
11 years ago
Featured
I hope that the Government / Land Dept.in Dubai can intervene and ensure that the Dubai Lagoon project is completed.We have had completion dates for more than 7 years given to us by Schon Properties and we have heard absolutely nothing from Town Centre Management.......How anyone can continually mislead people is beyond belief and someone has to intervene.
C
Corrado Pani
11 years ago
I live in UAE since 15 years , Investor in Dubai Lagoon Project. is true that This Project suffered very serious slowdowns. I sign my 2 apartment in December 2005 ( 10 years ago) trought better homes for the dubai lagoon . As a customer is frustrating to give money to people that have no clear answer for you in Dubai, the place where a choose to live, give my experience and support the country in is directions. I would like the Dubai government give us an answer to help to secure my savings of many years of hard work in this country and look at dubai as a place to plan a future foe me and my family. thank you
V
Vinod Thomas
11 years ago
I don't need to explain anything... I invested when I was 32 years old and now I am 42 years of age. This is my entire life's savings! I am sure the Government can fix this issue!
A
Abeera Atique
11 years ago
I am a teacher and therefore need some money to support my kids education. I bought this apartment thinking that I will get a resident UAE Visa and will be able to rent it out. But these 8 years have been extremely full of frustration and disappointments. I just dont know how to make Schon properties realize how many families have come in distress because of their false promises. I want nothing now but just my money back asap.
A
Anand Mohan
11 years ago
I am an overseas Investor in Dubai Lagoon Project. This Project sufferred very serious slowdowns now and in the past for more than 5-6 years and is no where to be seen in materialising it. The developer does not seem having any concern over their customers outstanding Problems. Fore more than 6 years they have been giving us odd completion dates which keeps on changing year after year. In front of Dubai Governmental authorities they managed to skip the Dates. How this is possible. I am not worried about the 4% but even it is done, what guarantee do we (Investors) have from regulatory organisations in Dubai?
C
Claudio Casagrande
11 years ago
I'm an 78 years old italian investor that bought a unit in the DL project as investment for my sons. I'll never see the finished unit neither I'm able to guarantee the investment to my sons.
C
Claudio Casagrande
11 years ago
Featured
I'm an 78 years old italian investor that bought a unit in the DL project as investment for my sons. I'll never see the finished unit neither I'm able to guarantee the investment to my sons.
I bought studio in 2014 & paid the 4% but nothing happened yet & they said I can't get my apartment in 2016 as agreement! :( From Kuwait
I bought studio in 2014 & paid the 4% but nothing happened yet & they said I can't get my apartment in 2016 as agreement! :( From Kuwait
I booked the apartment in 2008 and am still waiting for delivery. I am not sure if the project will ever be completed. The registration fee should be taken only on handover after completion.
I've also invested in this project. And totally agree that the registration fee should be delayed till completion of full project as already too delayed for this project
Worst decision I made in my life was to invest in Dubai Lagoon !
Why have RERA, DLD, Dubai Municipality, Dubai Government allowed Schon/TCM to continually mislead investors for 10 years? This is a partnership of companies that hasn't finished a single project in 10 years! How is it possible that they haven't been held accountable for holding investors money for 10 years with no sign of completion? Dubai needs to think about the damage this kind of "businessmen" do to its reputation. Expo 2020 is 5 years away and Dubai Lagoon is sending the wrong message about the safety of investments here.
I will gladly pay but I don't believe my developer intends to complete the project. It is already 8 years late.
I support this petition. I am a buyer in zone 1.
10 Years I have been waiting. 10 Years ago Pope John Paul 11 died, Angela Merkel became Germanys first Female Chancellor and the Burj Khalifa was just being started. No amount of compensation is going to be enough. Get on with it!!!
Really pathetic Situation. This developer keeps on dragging the dates of Project completion. Please do something Dubai Land Department for the DL Investors!
High time to intervene by Dubai Land Department as many years passed by. So far very pathetic result from the Developer. Please do something for and on behalf of DL Investors!
I have been waiting for my apartment for over 5 years
I would request the authorities not just to keep the registration fee payable at handover but also to refrain from capriciously changing the rules from day to day in all cases. Such actions don't help the real estate sector but greatly undermine people's trust and confidence in the sector when rules are whimsically changed and even applied retrospectively whenever it strikes the fancy of some authority. This particular change has significant implications not just for end users and investors alike who have lost huge sums on projects that never materialized but also for those who have budgeted as per the previous practice (registration payment at handover) and now face a shortfall. I would urge the authorities not to underestimate the importance of stability and clarity in the market and to try to work with people rather than against them through constructive regulations that are well thought out before implementation. Therefore, kindly reconsider this new demand at the earliest as it is very shortsighted and disappointing, and only harms the market.
I hope that the Government / Land Dept.in Dubai can intervene and ensure that the Dubai Lagoon project is completed.We have had completion dates for more than 7 years given to us by Schon Properties and we have heard absolutely nothing from Town Centre Management.......How anyone can continually mislead people is beyond belief and someone has to intervene.
I live in UAE since 15 years , Investor in Dubai Lagoon Project. is true that This Project suffered very serious slowdowns. I sign my 2 apartment in December 2005 ( 10 years ago) trought better homes for the dubai lagoon . As a customer is frustrating to give money to people that have no clear answer for you in Dubai, the place where a choose to live, give my experience and support the country in is directions. I would like the Dubai government give us an answer to help to secure my savings of many years of hard work in this country and look at dubai as a place to plan a future foe me and my family. thank you
I don't need to explain anything... I invested when I was 32 years old and now I am 42 years of age. This is my entire life's savings! I am sure the Government can fix this issue!
I am a teacher and therefore need some money to support my kids education. I bought this apartment thinking that I will get a resident UAE Visa and will be able to rent it out. But these 8 years have been extremely full of frustration and disappointments. I just dont know how to make Schon properties realize how many families have come in distress because of their false promises. I want nothing now but just my money back asap.
I am an overseas Investor in Dubai Lagoon Project. This Project sufferred very serious slowdowns now and in the past for more than 5-6 years and is no where to be seen in materialising it. The developer does not seem having any concern over their customers outstanding Problems. Fore more than 6 years they have been giving us odd completion dates which keeps on changing year after year. In front of Dubai Governmental authorities they managed to skip the Dates. How this is possible. I am not worried about the 4% but even it is done, what guarantee do we (Investors) have from regulatory organisations in Dubai?
I'm an 78 years old italian investor that bought a unit in the DL project as investment for my sons. I'll never see the finished unit neither I'm able to guarantee the investment to my sons.
I'm an 78 years old italian investor that bought a unit in the DL project as investment for my sons. I'll never see the finished unit neither I'm able to guarantee the investment to my sons.