I VOTE NO to the Virginia Street Sidewalk Installation Project Project Description: Installation of handicap accessible sidewalks and ramps on the West side of Virginia Street from Windsor Lane to Varela Street. Budgeted Amount: $165,550.00 Funding Source(s): FDOT Expected Start Date: May 2011 Expected Completion Date August 2011: City Project Manager: Karen Olson Contractor Design: Hole Montes, Inc. Contractor: Construction Charley Toppino.